| Name of Mine, Production Facility or Transport Operation | Signatory Ownership Position | Name of Operating Company |
Operation Address/Location |
Operation Coordinates | Certification Intention? | Additional Information or Comments | Date of Certification | Audit Documents |
| Lone Tree | 100% | Newmont USA Limited | PO Box 388, Valmay, Nevada 89438 USA |
40º47'40.38"N 117º7'35.65"W |
Yes | The mill at Lone Tree is no longer in production, but gold is still being produced via the heap leach process which may continue for another year or two. Site has been certified. | February 1, 2007 | Summary Audit Report Auditor Credential Form |
| Midas | 100% | Newmont Midas Operations Inc. | 1001 Gold Street, HC 66 Box 125, Midas, Nevada 89414 USA |
41º14'42.00"N 116º46'40.80"W |
Yes | Certification by 11/3/08 | ||
| Twin Creeks | 100% | Newmont USA Limited | PO Box Drawer 69, Golconda, Nevada 89414 USA | 41º15'30.11"N 117º10'7.63"W |
Yes | Site has been certified. | April 2, 2007 | Summary Audit Report Auditor Credential Form |
| Carlin | 100% | Newmont USA Limited | PO Box 669, Carlin, Nevada 89822 USA |
40º46'52.84"N 116º11'08.49"W |
Yes | Certification by 11/3/08 | ||
| Phoenix | 100% | Battle Mountain Gold Ltd. | PO Box 1627, Copper Canyon, Battle Mountain, Nevada 89820 USA | 40º30'35.72"N 117º08'16.77"W |
Yes | Need to provide ICMI with production date. | ||
| Minera Yanacocha | 51.35% | Newmont Peru S.R.L. | Minera Yanacocha SRL, Av. Victor Andres Belaunde 147, Via Principal 103 - Edificio Real Diez - Piso 4, Lima 27 Peru |
6º59'38.54"S 78º31'55.03"W |
Yes | Expected to be fully certified in the next few weeks. | April 1, 2008 | Summary Audit Report Auditor Credential Form |
| Waihi | 100% | Waihi Gold Company Ltd. | PO Box 190, Waihi, New Zealand 2981 | 37º23'8.06"S 175º50'30.65"E |
Yes | Certification by 11/3/08 | ||
| Pajingo | 100% | Newmont Pajingo Pty Ltd. | PO Box 1271, Charters Towers, Queensland, 4820 Australia | 20º31'45.44"S 146º21'18.54"E |
No | Operation sold Q4 2007. | ||
| Tanami | 100% | Newmont Tanami Pty Ltd. | PO Box 8020, Alice Springs, Northern Terrority, 0871, Australia | 19º57'52.50"S 129º42'20.24"E |
Yes | Certification by 11/3/08 | ||
| Jundee | 100% | Newmont Yandal Operations Pty Ltd. | PO Box 1652, Subiaco, Western Australia, 6904, Australia | 26º21'40.31"S 120º35'06.39"E |
Yes | Certification by 11/3/08 | ||
| KCGM | 50% | Kalgoorlie Consolidated Mines Pty Ltd. | PMB 27, Kalgoorlie, Western Australia, 6430, Australia | 30º46'39.11"S 121º30'14.72"E |
Yes | Newmont is a 50% JV partner with Barrick and the operation is run by Kalgoorlie Consolidated Gold Mines. Newmont may recommend to the operator (KCGM) to certify the Cyanide Code, but cannot require that they do so; therefore, it is Newmont's decision that the determination to list will be made by KCGM. | ||
| Ahafo | 100% | Newmont Ghana Gold Ltd. | PMB Airport Post Office, East Legon, Accra, Ghana | 7º1'32.016"N 2º20'52.728"W |
Yes | Site has been certified as compliant with the Cyanide Code. | March 20, 2008 | Summary Audit Report Auditor Credential Form Corrective Action Plan |
| Akeym | 100% | Golden Ridge Resources Ltd. | PMB Airport Post Office, East Legon, Accra, Ghana | 06º21'38.20"N 01º01'36.70"W |
No* | *Will eventually be certified. Project still in early design and initial permitting. No material construction anticipated in 2008. No production. | ||
| Boddington | 66% | Boddington Gold Mine Management Company Pty Ltd. | PO Box 48, Boddington, Western Australia, 6390 Australia | 32º43'59.06"S 116º25'48.92"E |
No* | *Will eventually be certified. Project still in development phase. CN Code Certification will occur within 3 years of beginning of production. | ||
| Kori Kollo | 88% | Empresa Minera Inti Raymi S.A. | Av. Fuerza Naval No. 55, Calacoto, Boliva | 17º47'55.11"S 67º27'19.32"W |
No | Current mine plans have Kori Kollo closing in 2009. |